03.13.2025 e-news
03.13.2025 Building Our Vision Update
Progress continues on heating and insulation. You can see int he photo above where they are making space for one of the returns in the Sanctuary.
The external work on finalizing foundations also continued this week, working on getting elevations correct,a nd making the new additions … read more.
03.09.2025 Order of Service
03.06.2025 e-news
03.06.2025 Building Our Vision Updates
Progress continues on heating and insulation. The Parish House boiler is up and running, and the sanctuary heating system is in progress, with lots of new ductwork and equipment fitting in to our cramped old space.
The new narthex/lobby is full framed in and you can … read more.
03.02.2025 Order of Service
02.27.2024 e-news
02.27.2025 Building Our Vision Update
We have had more progress on the foundation to our new entrance this week. The concrete was poured and we now have a visible foundation. Work on the new boilers continued and the heat was turned on in the sanctuary and parish house. Inside the … read more.