Author: Ericka Lavalley

12.12.2024 Building Our Vision Updates

Our crew got a ton of external demo work done this week! Both connectors are completely gone other than the foundations. The fence is beginning to come down, as well as the stairs. Inside, they are continuing to work on prepping the basement for the … read more.

12.05.2024 Building Our Vision Update

This week the crew continued with internal demolition, the focus being in the sanctuary.  The Sanctuary doors were removed, both inside and outside, a wall came down, carpet was removed and the remainder of the chancel was removed this week.  We have had electricians on … read more.

11.27.2024 Building Our Vision Update

This week was a lot of internal prep for for demolition and site work to begin next week. All the electrical was made safe, and they started prepping pieces for a temporary wall that block off the White Wing Building from the construction zone. Next … read more.