03.06.2025 Building Our Vision Updates
Progress continues on heating and insulation. The Parish House boiler is up and running, and the sanctuary heating system is in progress, with lots of new ductwork and equipment fitting in to our cramped old space.
The new narthex/lobby is full framed in and you can … read more.
03.02.2025 Order of Service
02.27.2024 e-news
02.27.2025 Building Our Vision Update
We have had more progress on the foundation to our new entrance this week. The concrete was poured and we now have a visible foundation. Work on the new boilers continued and the heat was turned on in the sanctuary and parish house. Inside the … read more.
02.23.2025 Order of Service
02.20.2025 e-news
02.20.2025 Building Our Vision Updates
It has been exciting to see the progress on foundations this week. The footings are in and they are getting ready for walls. The work on the Sanctuary heat pump system is in full swing, with lots of details to figure out when it comes … read more.